Introduction to MRO

The MRO (Maintenance, Repair, and Overhaul) app is designed to reduce turnaround time and enhance customer satisfaction by addressing key challenges in the maintenance industry.

Y
Written by Yosr Laatar

1. What the MRO app is for

MRO means Maintenance, Repair and Overhaul. It works differently from manufacturing. You are not producing to a plan. You are reacting to equipment that arrives when it breaks.

The app exists to make that reactive work manageable.

The three goals

Goal

What it means day to day

More on-time delivery

You meet the dates you promised your customer

Less turnaround time

The cycle from arrival to shipment gets shorter

Better team productivity

Less time looking for information, more time fixing problems

The problems it solves

Problem

Why it is hard

Repair demand is unpredictable

You cannot plan for breakdowns the way you plan production volume

Repair lead times are hard to see

Without visibility, a stalled order looks the same as a moving one

Priorities compete

Several orders need the same scarce part, and the shop floor does not always work on what matters most

Volumes keep rising

Older equipment creates more MRO orders every year

Logistics visibility is poor

Parts, subcontractors and internal repair loops all move at different speeds

The app answers these by keeping everything in one place: what each service order needs, what is missing, when capacity runs out, and what to do first.

💡 The key MRO insight is that you often do not need more stock. You need the right orders served first. If several service orders need the same scarce part, and some are missing one component while others are missing many, serving the nearly finished ones closes more orders with the same stock. See Simulations for how to test this before you commit.


2. Which view should I use?

The app has four views. Each one answers a different question.

If you are asking

Open

"What is the state of my service orders?"

Service Order Book, table view

"Which orders are blocked, and by which part?"

Service Order Book, heatmap view

"What is missing, and since when?"

Missing Part view

"Will I have the capacity to do this work?"

Capacity view

"What happens if I change my priorities?"

Simulations. See the separate article.


3. Service Order Book

This view lists all your maintenance work, ongoing and scheduled. You use it to check status, follow progress, and confirm that orders will finish on time. Each order carries its context with it: who is assigned, which parts it needs, and its planned timeline.

3.1 Table view

Every service order appears as a row. Each row is a piece of equipment, with its service order number and serial number. Orders are sorted by date, oldest first.

Column

What it shows

Status

Combines service order coverage, delivery status and commercial status. Hover over it for the detail behind the figure.

Service Order

The service order number.

Equipment

The ID or reference number of the equipment.

SN

The serial number of the equipment.

Required Cov

When the component is needed, and when the stock projection algorithm allocates parts to it.

Revised Due

The completion date negotiated and agreed between you and your customer. Always populated, and the date Pelico uses to calculate on-time delivery.

Reception

The date the module was physically received.

Customer Req. Date

The date the customer originally asked for, before any negotiation. Can be contractual. Hidden by default.

<aside>
💡

Revised Due and Customer Req. Date are not the same date. Customer Req. Date is what the customer asked for on their own. Revised Due is what you and the customer agreed after discussing it. When the original request could be met as-is, the two match. When it could not, Revised Due is the commitment that replaced it.

This matters because on-time delivery is measured against Revised Due, not against what the customer first asked for.

</aside>

3.2 Heatmap view

The heatmap sits next to the table view. Here the columns are the parts your MRO operations need, and the rows are your service orders. It is the fastest way to see which part is blocking which order.

Reading a column header. Each header is the name of a part, and it is clickable — selecting it opens further actions on that part.

Reading a cell. Stock appears as XX / YY:

  • XX is the stock required to execute all MRO orders.

  • YY is the stock currently available.

Colour code for stock levels

The colour answers one question: does current stock cover what the service orders need?

Colour

Meaning

🟢 Green

Stock covers the need.

🟡 Yellow

The need is conditionally covered — supply is expected in time.

🔴 Red

Stock does not cover the need, or the supply arrives too late.

<aside>
💡

Some views express this as a shortfall figure rather than a stock figure. Where you see a number described in terms of used parts, read it as demand minus available stock: a positive value is the quantity still missing, so it turns the cell red. Zero or below means stock covers the demand. The number measures the gap, not what is on the shelf — which is why a positive value is bad news.

</aside>

<aside>
💡

The heatmap is the starting point for most MRO work: allocating a scarce part, unblocking an order after kitting, escalating a shortage. See MRO Usage Scenarios.

</aside>


4. Missing Part view

This view shows the parts holding up your service orders, on a timeline. Each line gives you enough context to act on the part instead of just noting it.

Element

What it tells you

Blocking Date

The date when the part will block production.

Required Part

The specific part needed.

Plant

The location where the part is needed.

Parent Equipment

The equipment the part belongs to.

Part Type

Whether the part is M, B, or M&B — Make, Buy, or both.

Related Events

Supply events, and any Stock Transfer Opportunities (STO).

Days Until Missing

How many days until the part runs out, with the break date.

Colour coding

Colour

Meaning

🔴 Red

The part is blocking production.

🟡 Yellow

The part is conditionally covered.

<aside>
💡

Days Until Missing is the column to sort on. Blocking Date tells you when a part becomes a problem; Days Until Missing tells you how long you have left to do something about it.

</aside>


5. Capacity view

This is the only place in Pelico where work centre capacity is modelled. Capacity is set as hours per week, per work centre.

What it gives you

  • Early warning of blockages. You see where repair work will stall before it does.

  • Load against capacity. You see the work you have next to the hours you have. Bottlenecks become visible instead of something you guess at.

💡 This view has no equivalent in Production Control. The Suggested Start Date in the Work Order Book ignores capacity on purpose. It tells you when material and upstream work allow a start, not whether you can take it. If capacity is your constraint, this is the view that tells you.


6. Planned workload vs capacity

This extends the Capacity view by adding forecast demand, so your capacity analysis reaches beyond firm orders.

Feature

What it gives you

Sales forecasts included

Forecasts enter your planning early, so you can see blockages coming

Effect on workload

Forecasts feed the workload, which lets you compare load and capacity over the long term

Material needs shown

You see how forecast demand turns into material needs, and where that creates bottlenecks

Filtered analysis

You can limit the analysis to the work centres you care about

Work centre heatmap

Week by week view of blockages across all work centres, over the coming months

Blockage indicator

A status flags any service order that needs a work centre with too little capacity that week

💡 The blockage indicator is worth understanding. It is a capacity problem, not a material one. A service order can have every part it needs and still be flagged, because the work centre it needs is overloaded that week. That is a different problem with a different fix: move capacity, or move the work.

⚠️ Pelico uses the word "heatmap" for two different views. The heatmap view in the Service Order Book shows service orders against blocking parts. The work centre heatmap here shows work centres against weeks. They are not the same.


7. How MRO connects to the rest of Pelico

Coverage works the same way in MRO as everywhere else in Pelico. A service order gets the worst coverage status among the parts it needs, and the statuses mean the same thing: covered from stock, conditionally covered while supply is expected, or blocked with no solution.

Topic

Where to read about it

Coverage, stock projection, pegging

Pelico's Algorithms

Testing a change before you commit to it

Simulations

Simulating gate commitments to reduce work in progress

Simulations, MRO section

Escalation tickets and tiers

Introduction to Production Control


8. FAQ

How is MRO different from Production Control?

Production Control manages work orders against a production plan. MRO manages service orders against repair demand that arrives without warning. The coverage logic is the same. The views, the priority questions and the capacity model are different.

Why is my service order blocked when all its parts are available?

Check whether it is a capacity blockage rather than a material one. A service order that needs a work centre with too little capacity in a given week gets its own status, separate from material coverage.

Where do I see work centre capacity?

In the MRO Capacity view. It is set in hours per week per work centre, and it is the only capacity model in Pelico.

Do sales forecasts change my MRO plan?

Yes, where they are switched on. They feed the workload used for long-term load and capacity analysis, and Pelico shows what they mean for material.

Do coverage statuses mean the same thing in MRO as in Production Control?

Yes. Covered, conditionally covered and blocked are calculated the same way. See Pelico's Algorithms.


9. Glossary

Term

Definition

Blocking date

The date from which a missing part starts holding work up.

Capacity view

The MRO view comparing workload against work centre capacity.

Load vs capacity

The work you have to do compared with the hours available at a work centre.

MRO

Maintenance, Repair and Overhaul.

OTD

On-time delivery.

Rotable

A repairable part kept in a pool and exchanged rather than replaced. (definition to confirm)

Service Order (SO)

An order to maintain, repair or overhaul a piece of equipment.

Service Order Book

The view listing all service orders with their status and context.

Turnaround time (TAT)

The time from equipment arrival to shipment.

Work centre

A resource with a limited number of hours available each week.

WIP

Work in progress. Repair work started but not finished.


10. Visual content to add

This article has a specific problem: two of its sections have no content, so their visuals cannot be produced yet. The list below separates what can be done now from what has to wait.

Can be produced now

Visual

Type

Why it helps

Priority

The four MRO views side by side

Diagram: four labelled panels, each with the question it answers

Section 2 is the most useful part of this article. A single image makes the choice of view obvious.

High

Material blockage vs capacity blockage

Diagram: two service orders, one missing a part, one needing an overloaded work centre, both flagged

This is the most confusing point in MRO. Readers assume every blockage is a material blockage.

High

Load vs capacity over weeks

Diagram or annotated screenshot: bars of planned load against a capacity line, with one week over the line

Shows what "capacity blockage" actually looks like, and which week to act on.

High

The two heatmaps, labelled

Two annotated screenshots side by side: service orders × blocking parts, and work centres × weeks

Pelico uses the same word for both. Showing them together prevents a real misunderstanding.

Medium

Serving nearly finished orders first

Diagram: four service orders competing for one scarce part, showing how many close under two different allocation choices

This is the core MRO insight and it is hard to grasp from a paragraph.

Medium

Missing Part view, annotated

Screenshot with each of the six fields labelled

Turns the table in section 4 into something a reader can match to their screen.

Medium

Where MRO sits next to Production Control

Diagram: shared coverage engine, different views on top

Helps users who work in both apps stop expecting MRO to behave like PC.

Low

Waiting on content

Visual

Blocked by

Service Order Book table view, annotated with columns

Section 3.1 has no column reference yet

Heatmap view with its colour legend

Section 3.2 has no content yet

A lightbulb on a red cell, showing a rotable opportunity

Needs the rotable definition and detection rules

The service order lifecycle through its gates

Gates are never defined in the current documentation

💡 That last one deserves attention. A diagram of the service order lifecycle through its gates, including the kitting gate, would probably be the single most valuable visual in the whole MRO section. Gates appear throughout the documentation and are never explained. Right now we cannot draw it, because nobody has written down what the gates are.


Before publishing. Replace the table of contents marker with a native /table of contents block. Convert the 💡 blocks to blue callouts and the ⚠️ blocks to yellow callouts. Add Notion links to #8 Pelico's Algorithms, #4 Simulation and #7 Production Control.

This article is publishable as it stands. It is more complete than the source. But the two most used views in the app still have no column reference, and readers will notice. See the MRO questions in #0 Pilotage.


Questions to test with Fin

  1. What is the difference between Revised Due and Customer Req. Date on a service order ?

  2. What do the two numbers in a Service Order Book heatmap cell represent ?

  3. What is the difference between the heatmap view in the Service Order Book and the work centre heatmap ?

  4. How is work centre capacity measured in the MRO Capacity view ?

  5. What does the Days Until Missing column tell me ?